WEBVTT 00:00.930 --> 00:03.009 The US Army Corps of Engineers Tulsa 00:03.009 --> 00:04.898 District is tackling a dam safety 00:04.898 --> 00:07.065 repair at Oligo Dam in Rogers County , 00:07.130 --> 00:10.149 Oklahoma . So we're installing a new 00:10.149 --> 00:12.149 stelling basin and repairing an old 00:12.149 --> 00:14.093 stelling basin . What the stelling 00:14.093 --> 00:16.450 basin is , is it is a platform that is 00:16.450 --> 00:18.690 designed to reduce erosion as well as 00:18.690 --> 00:21.360 slow down the rapids directly out of 00:21.360 --> 00:24.170 the gate . During a 2022 inspection , 00:24.409 --> 00:26.742 engineers identified damage to concrete . 00:26.850 --> 00:29.128 We actually had an advanced study done . 00:29.128 --> 00:31.350 In the Stilling basin , they found that 00:31.350 --> 00:33.406 it was actually the fine particles , 00:33.406 --> 00:35.294 sediment particles that would get 00:35.294 --> 00:37.572 trapped within the Stilling basin , um , 00:37.572 --> 00:39.406 that would cause ball milling in 00:39.406 --> 00:41.406 between the baffle blocks that over 00:41.406 --> 00:44.694 time just releases below 3000 CFS were 00:44.694 --> 00:48.055 causing greater damage . Each 19 ft 00:48.055 --> 00:51.895 conduit can release up to 17,500 cubic 00:51.895 --> 00:55.354 feet , about 131,000 gallons , 00:55.575 --> 00:58.330 every second . Even at half capacity , 00:58.409 --> 01:00.465 the water from a single conduit hits 01:00.465 --> 01:03.159 the basin floor with over 3.8 million 01:03.159 --> 01:05.260 pounds of force . That's more than 01:05.260 --> 01:07.819 twice the thrust a Falcon 9 rocket 01:07.819 --> 01:10.779 produces during liftoff . So whenever 01:10.779 --> 01:13.080 we're really seeing a max discharge out 01:13.080 --> 01:15.024 of the conduits , we're looking at 01:15.024 --> 01:18.900 approximately 35,000 CFS . At that rate , 01:19.099 --> 01:22.339 we'll see anywhere from in the millions 01:22.339 --> 01:24.940 pound force . Before any concrete work 01:24.940 --> 01:26.662 begins , contractors use heavy 01:26.662 --> 01:28.773 equipment to construct a cofferdam in 01:28.773 --> 01:30.884 the Verdigris River downstream of the 01:30.884 --> 01:33.107 work area and are currently pumping the 01:33.107 --> 01:35.769 basin dry . Engineers expect the 01:35.769 --> 01:38.110 project to wrap up in about 10 months .